Suyog Gurbaxani Funicular Ropeways has been awarded the work to design, engineer, procure, finance, construct, operate and maintain Funicular Ropeway on Build, Operate & Transfer (BOT) basis at Saptashrungi Gad, Vani, Kalwan, Nashik, and to charge and collect the toll fees as per Concession Agreement dated 12.01.2010, executed with Government of Maharashtra, Public Works Department.
2010
Incorporation of the Company
Received Work Order for construction of Funicular Ropeways at Saptashrungi
Forest Department granted 4 hectare of land for construction of project
Possession for the above land received
Received Water permission for the project from the Maharashtra Water Department
Received consent of Gram pachayat for construction of the Project
2010
2011
The plan / drawing for the project with single track system approved by the PWD Steering Committee
Obtained confirmation from RITES to act as technical consultant for the single track project
2011
2012
Obtained RITES confirmation for change in project plan to double track instead of single track
2012
2013
Received consent from Temple Trust to build machine room near the temple
2013
2014
Extension request letter given to PWD by the Company citing various statutory clearance delays and change in plans
2014
2015
The official Project management Consultant certified that the construction of the Funicular ropeway is as per approved drawings & specification of PWD
2015
2017
Extension Approval for 3 years 1 month and 27 days received from the PWD, Nashik
Foreign Safety Consultant suggested additional braking facility before certifying the safety measures of the Funicular Ropeway
Final Safety Certificate received from Tribal Public Works Division
2017
2018
Received certificate from Damodar Ropeways Private Limited confirming the employee training for operating the Funicular Ropeway
Received provisional Completion Certificate from PWD, Nashik
Fire NoC received for operating the Ropeway for Public use
Construction Completed and Inaugration by Hon. Chief Minister of Maharashtra Mr. Devendra Phadnavis
2018
2019
Final Completion Certificate received from PWD, Nashik Â
2019